ruohki 539efdc202 docs(02-03): complete app integration plan — Phase 2 all 3 plans done
- Create 02-03-SUMMARY.md documenting DocumentState, scrolling, status bar, error screen
- Update STATE.md: Phase 2 complete, 6 total plans, Phase 3 next
- Update ROADMAP.md: Phase 2 all 3 plans SUMMARY present, marked Complete
- Mark NAV-05, NAV-08, NAV-09 requirements complete in REQUIREMENTS.md
2026-02-28 22:26:19 +01:00
ruohki b6069d90e5 docs(02-02): complete markdown renderer plan — REND-01 through REND-10 satisfied
- 02-02-SUMMARY.md: documents render_markdown() pipeline, code block borders, GFM table grid, decisions, deviations
- STATE.md: advance to plan 02 done, update decisions log (02-02 entries), resolve REND Widget trait blocker
- ROADMAP.md: mark 02-02 complete (2/3 plans done for Phase 2)
2026-02-28 22:20:35 +01:00
ruohki af0fe03f12 docs(02-01): complete vault core and highlighter foundation plan
- Add 02-01-SUMMARY.md with full execution record and deviation documentation
- Update STATE.md: Phase 2 Plan 1 complete, resume at 02-02-PLAN.md
- Update REQUIREMENTS.md: mark REND-03, REND-10, NAV-06, NAV-07 complete
2026-02-28 22:14:20 +01:00
ruohki ae379b62f6 docs(02): create phase plans (3 plans, 3 waves) 2026-02-28 22:08:57 +01:00
ruohki ab71c42c6b docs(02): create phase plan 2026-02-28 22:02:14 +01:00
ruohki 24f11f39be docs(02): research vault core and rendering phase 2026-02-28 21:55:13 +01:00
ruohki 7222543d4c docs(02): capture phase context 2026-02-28 21:44:22 +01:00
ruohki 88f665a095 test(01): complete UAT - 8 passed, 0 issues 2026-02-28 21:35:20 +01:00
ruohki 240ae4aace test(01): complete UAT - 7 passed, 1 issue 2026-02-28 21:32:29 +01:00
ruohki 90dc4882ae docs(phase-1): complete phase execution 2026-02-28 21:24:04 +01:00
ruohki d9db04fb01 docs(01-03): complete app event loop and Phase 1 wiring plan
- 01-03-SUMMARY.md: documents App struct, event loop, double-Ctrl+C state machine, main.rs pipeline
- STATE.md: Phase 1 complete, 3/3 plans done, Phase 2 next, 01-03 decisions recorded
- ROADMAP.md: Phase 1 marked Complete (3 plans / 3 summaries)
- REQUIREMENTS.md: SHEL-01 marked complete
2026-02-28 21:20:02 +01:00
ruohki d6209ba4c5 docs(01-02): complete terminal safety primitives plan 2026-02-28 21:14:44 +01:00
ruohki c97c149366 docs(01-safety-foundation): create phase plan 2026-02-28 21:05:46 +01:00
ruohki 88a93c16ed docs(01): research phase 1 safety foundation 2026-02-28 20:58:46 +01:00
ruohki d537f04bf6 docs(01): capture phase context 2026-02-28 20:49:44 +01:00